Nation Rise Wind Farm

ON-Nation-Rise-Hero.jpg
Wind

Nation Rise Wind Farm

Monday 28, September 2020
Installed capacity of 100 megawatts

Project overview

Nation Rise Wind Farm is located approximately 40 kilometers southeast of Ottawa, ON. The Nation Rise Wind Farm is situated in the Municipality of North Stormont within the United Counties of Stormont, Dundas, and Glengarry. The area is mainly comprised of agriculture land predominantly used for dairy farming, corn, and soybeans.

The Nation Rise Wind Farm was submitted in the 2015 Large Renewable Procurement I (LRPI) facilitated by the Independent Electricity System Operator (IESO). In March 2016, the Nation Rise Wind Farm was a Selected Proponent in the IESO's LRP I and was awarded a contract to provide Ontario with 100MW of clean, renewable energy. The project was granted its Renewable Energy Approval (0871-AV3TFM) on May 4th, 2018.

The Nation Rise Wind Farm successfully achieved commercial operation on June 14th, 2021 as confirmed by the Ontario IESO and will provide renewable electricity to Ontario for a period of 20 years.

Economic benefits

Nation Rise Wind Farm yields significantly in the form of payments to landowners, local spending, and annual community investment. Nation Rise Wind Farm is also compatible with other land uses and provides a stable form of income to local landowners.
$30+ million
Total project impact
$383,667
Paid to local governments
$4.6 million
Paid to landowners
$25.1 million
Spent locally
Job creation
69 construction jobs and 7 permanent jobs created
ON-Nation-Rise-Impact.jpg

The impact of Nation Rise Wind Farm

Watch what the community is saying about Nation Rise Wind Farm

Renewable energy technology

wind_turbine_arkwright01.jpg

Energy security

Nation Rise Wind Farm helps strengthen energy security for Canada, helping diversify domestic supply.
wind_turbine_arkwright02.jpg

Wind energy and land use

Wind turbines have a limited footprint, leaving 98% of the project’s leased land available for farming, or wildlife habitat.
quiltblock_edpr_chelseaparrett_41-133.jpg

Wind energy and American manufacturing

450+ American factories produce parts and materials for the U.S. wind industry, which employs 130,000+ Americans.
Nature_Stream_decarbonization.jpg

177 million gallons of water saved each year

Nation Rise saves more than 177 million gallons of water each year and prevents the air pollution that causes smog, acid rain, and climate change.

Downloads

About EDPR NA
Document
PDF . 2.83 MB
Search
Nation Rise - Emergency Response Plan – Operations
Document
PDF . 129.71 KB
Nation Rise - Turbidity Sampling Program
Document
PDF . 188.91 KB
Nation Rise - MECP Letter of Approval – Turbidity Sampling Program
Document
PDF . 42.58 KB
Nation Rise - Spill Control and Response Plan
Document
PDF . 220.16 KB
Nation Rise - Erosion and Sediment Control Plan
Document
PDF . 503.03 KB
Nation Rise - Stormwater Management Plan
Document
PDF . 3.14 MB
Nation Rise - MECP Letter of Approval – Stormwater Management Plan, Erosion and Sediment Control Plan, Spill Control and Response Plan
Document
PDF . 34.66 KB
Nation Rise - MECP Letter – Geotechnical Report Scope of Work
Document
PDF . 31.41 KB
Nation Rise - REA Condition R1 – Geotechnical Report Scope of Work
Document
PDF . 140.46 KB
Nation Rise - MECP Letter of Approval – Pre-Construction Well Survey Report
Document
PDF . 23.37 KB
Nation Rise - Water Well Complaint Response Procedure and Contingency Plan
Document
PDF . 1.17 MB
Nation Rise - MECP Letter of Approval – Water Well Complaint Response Procedure and Contingency Plan
Document
PDF . 24.09 KB
Nation Rise - MECP Letter of Approval – Groundwater Monitoring Program
Document
PDF . 24.25 KB
Nation Rise- MECP Letter of Approval- Groundwater Monitoring Program
Document
PDF . 24.25 KB
Nation Rise - Geotechnical Report – Pre-Construction Road Condition Survey Data
Document
PDF . 13.79 MB
Nation Rise - Geotechnical Report – MET Tower
Document
PDF . 10.60 MB
Nation Rise - Geotechnical Report – Overhead and Underground Collection System
Document
PDF . 9.87 MB
Nation Rise - Geotechnical Report - Substation
Document
PDF . 10.18 MB
Nation Rise - Geotechnical Report – Wind Turbine Generator Foundations
Document
PDF . 83.16 MB
Nation Rise MECP Letter of Approval – Condition R1, Geotechnical Reports
Document
PDF . 43.50 KB
Nation Rise - Emergency Response Plan – Primary Construction
Document
PDF . 1.09 MB

Home Improvement Fund

The Home Improvement Fund (HIF) was established as part of an agreement between the Concerned Citizens of North Stormont (CCNS) and the Nation Rise Wind Farm to provide households within 1.5 kilometers of wind turbines the opportunity to apply for funding for home improvements that will mitigate perceived noise or visual impacts from the operation of the project.

A one-time $150,000 donation will be made by the Nation Rise Wind Farm to the HIF which is available now that the project has reached commercial operations. The application period is open and will close July 14th, 2022 and the fund will be distributed in late summer 2022. Application forms for the fund have been provided under the Home Improvement Fund section of the downloads section. A map of the catchment area and a list of all homes within the area has also been provided for download. Interested applicants are advised to review these documents for eligibility and for further information on the HIF and application requirements.

Search
Nothing to show here
Change your filters and search again
Contact us

Nation Rise Wind Farm

Operations & Maintenance Office
4344 County Road 16
Brinston, ON, L0E 1C0